Yields all 8 short posts. Cut individually AFTER blocks are leveled.
4 10' stick
2x10 PT
ground contact UC4A
Skirtboard, all four sides
11 10' stick
2x8 PT
—
9 joists at 117" + 2 spare
4 8' stick
2x8 PT
—
Pier blocking, ring blocking, bay blocking
24 10' board (installs 21)
5/4 x 6 PT decking
actual 1" x 5.5"
Rated for 16" o.c. Extra covers hatch sub-frame and culls.
4 10' board
1x or 5/4 fascia
—
Skirt. Stop 2" above grade for ventilation.
Deck hardware
Qty
Item
Spec
Notes
20 each
2x8 face-mount joist hanger
hot-dip galvanized or stainless
9 joists x 2 ends + spares. No ledger — fastens to the 2x10 rim.
1 1 lb box
Joist hanger nails 1-1/2"
HDG
Hangers need hanger nails, not deck screws
16 set
3/8" x 6" carriage bolt + washer + nut
HDG or stainless
2 per post into the skirtboard
500 screw
GRK Deck Elite #9 x 2-1/2"
type-17 point, bugle head, Climatek coating
The type-17 point is what prevents splitting — not the gauge. No pre-drilling needed in 5/4.
1 can
End-cut preservative
—
Every PT cut
Pier — concrete and form
Qty
Item
Spec
Notes
12 bag
60 lb high-strength concrete mix
—
~5.4 cu ft for a 12" form to this height
1 each
Concrete form tube
12" diameter x 48"
Cut to length IN PLACE so the rim is the screed line. Set from grade up — it is a form, not structure.
4 10' bar
#4 rebar
1/2"
Cut to 70" for verticals. 50" offcuts become footing cross ties.
1 4' bar
#3 rebar
3/8"
Twelve 5" tie pieces need 60" of bar plus kerf, 12" more than one 4' bar holds. No bending required.
1 roll
Tie wire
—
Ties, and hanging the cage from the rim stick
4 each
Dobie blocks
3"
Or place a 4" base lift and set the cage into it. Never wood, brick or rock.
Pier adapter
Qty
Item
Spec
Notes
2 each
Brake rotor, solid
2012 Chevy Malibu — center bore fits the EQ6-R
Degrease thoroughly. Leave embedded faces bare.
4 each
1/2"-13 x 36" all-thread
304 stainless
Can never be replaced without destroying the pier. Hot-dip galvanized is equally correct.
20 each
1/2" hex nut
match rod material
5 per rod
8 each
1/2" fender washer
match rod material
2 per rod — top (spans 5/8" holes) and buried anchor
16 each
1/2" flat washer
match rod material
1 per rod used, rest spare
1 bottle
Nickel anti-seize
nickel-based, NOT PTFE or food-grade
Stainless galls. Exposed threads only — never on anything concrete touches.
4 each
Steel tube spacer
2" OD x 0.25" wall, cut to the chosen gap
Ends must be faced square and flat
1 assortment
Stainless shim stock
—
Leveling under the spacers
1 each
5/8" drill bit for cast iron
—
Top rotor only. Drill dry, 300-400 rpm, clamp the work.
Conduit and trench
Qty
Item
Spec
Notes
measure (10' stick)
1" PVC sch 40 conduit (gray electrical)
gray electrical, NOT white plumbing
Two runs. Quantity = run length + 20%, rounded to whole sticks, x2. Measure your distance to the house.
6 each
1" PVC sweep 90
long sweep
NEVER hard elbows — you will not pull Cat6 through one
1 set
PVC conduit cement + couplings
—
2 roll
Pull string / mule tape
—
Run before backfilling. Non-negotiable.
4 each
Conduit caps
—
Concrete inside a conduit ends that conduit permanently
Isolation
Qty
Item
Spec
Notes
1 each
Flexible pier collar / boot / loose trim ring⚑ Critical to isolation
—
Closes the 1-1/4" gap. Fastened to the DECK side only. Never caulk solid.
Wind anchoring
Qty
Item
Spec
Notes
4 each
Earth/auger anchor + cable or strap⚠ Unresolved — ask the manufacturer
—
UNRESOLVED — this is a floor, not a manufacturer spec. Ask NexDome about anchoring on a non-monolithic base.
Tools
Tool
Why
Rotary laser level or long straightedge + level
Eight blocks to a single plane
Post-hole digger or rented 12" auger
36" pier hole
Trenching shovel
18" conduit trench
Wheelbarrow or mixing tub + hoe
12 bags of concrete
25' steel tape, chalk line, speed square
Diagonals must read 169-11/16"
4' level
Form plumb in two directions
Torpedo level
Rotor at 0/45/90/135 degrees
Circular saw
—
Impact driver + socket set
Carriage bolts
Rebar cutter or angle grinder
Cutting bars to length
Hand tamper
Gravel pads in two lifts
Respirator + eye protection
Cast iron dust is fine and dark; wet concrete is caustic
Four choices worth explaining
Ground-contact PT (UC4A), not above-ground (UC3B) for posts, skirtboard, and
anything within 6" of soil. Small price difference, and it is the wet-climate
failure mode.
Hot-dip galvanized or stainless fasteners only. Modern PT chemistry destroys
electroplated fasteners — hangers, bolts, screws and nails alike.
304 stainless rods over cheaper options. Not for strength; the static load is
under 100 lb and any rod is overbuilt. These four rods can never be replaced
without destroying the pier, and the 6-1/4" bolt square leaves only 1.33" of
cover. Hot-dip galvanized would be equally correct — electroplated zinc would not.
GRK Deck Elite screws after three wrong answers. What prevents splitting in
5/4 decking is a type-17 auger point, not the gauge. A #10 stainless splits
without pre-drilling, a #7 stainless snaps heads in dense PT, and a trim head
pulls straight through decking.